A pair of fiendish supplements for Shadowdark and the wider OSR space!
Latest Updates from Our Project:
Update!
about 1 month ago
– Tue, Apr 28, 2026 at 11:26:28 AM
I think I should have everything I need for fulfillment by this weekend. I have been waiting on stuff from third parties and the last of it SHOULD be in my hands very soon. If all goes well, I plan to have all remaining packages (with completed surveys) shipped before the end of the next week (April 8).
Thank you for your patience.
No Sleep Till Brooklyn, Jeff Jones
Update April 9
about 2 months ago
– Thu, Apr 09, 2026 at 05:14:13 PM
Where do we stand on Fulfillment?
482 pledges fulfilled
42 backers have not filled out their surveys
6 backers have failed card transactions.
29 backers that I have all the material for and I still need to package and ship.
34 backers have items that am waiting to receive from three different people I partnered with:
Dice
Cards
Equipment pads
Minis
Here is the way I see things working out:
I expect ship to all the 29 backers by April 17th. We are down to package groups that only have, at most a few backers....these are much less efficient to package and label than packaging groups with more backers.
I expect to have goods in hand and all packages shipped out by the end of May.
When I receive the dice/cards/pads/minis I will provide an update.
I am a busy little bee and I appreciate you all.
No Sleep Till Brooklyn, Jeff Jones
Update Mar 28
2 months ago
– Sat, Mar 28, 2026 at 06:38:40 AM
Currently I am waiting on the delivery of hardcover books. This should happen any day (i expected it earlier this week)
I am working with the dice and mini people to get their product to me this month.
The supplier of equipment sheets and crawler cards is waiting on their shipment from overseas. If you have these as addons, your packages may be delayed a few weeks.
I started fulfillment for the non-US backers. Normally, I wait until all material is ready, but given the complexity of fulfillment, an upcoming convention and the convergence of fulfillment for another Kickstarter I started fulfillment with what I could.
We are getting close!
No Sleep Till Brooklyn, Jeff Jones
Quick Update
3 months ago
– Sun, Mar 08, 2026 at 05:25:25 AM
Hardcover books are due to arrive early April.
Proof copies from Lulu arrived for both Crawl and Dark Devilry. They both looked good but I need to re-order another proof copy of Dark Devilry as I have since updated the production PDF.
We are still on track for delivery by the end of April
If you are so inclined, check out my discussion with RPG historian, Shannon Appelcline.
No Sleep Till Brooklyn, Jeff Jones
Update!
3 months ago
– Thu, Feb 26, 2026 at 07:07:13 AM
Files are at the printer (Walsworth). I hope to start fulfilling books in April. There arae a lot of things converging for me at that time
Backerkit surveys are now sent, please get those filled out when you get a chance.
I will provide a more detailed update once things firm up a bit more. Everything is looking good.